D365 Project Service Automation

Non-Billable classification of task work around in PSA V3

Problem Definition:

As soon I upgraded my PSA version from V2 to V3, I saw that the role field got deprecated. Not only that, it was removed from Schedule (WBS in V2). We now had the functionality to directly assign resource to the task against having assign role.

The projects that got migrated from V2 to V3 were all tagged with the resource named “Auto-Developer” and were with the roles, but, was not advisable to go the deprecated way.

We now as an organization, heavily dependent on our day-to-day activities had to change the way we work and had to understand and reframe the working methodology for the following things:

  1. How to take care of the tasks that we need to make it Non-Billable
  2. Where to assign roles and learn to assign Resources instead.

Solution:

The above problem was not an easy cake to eat. The impact went all the way to Schedule Board and we need to redesign the way we allocate on tasks, since, I started seeing duplicate tasks on schedule board, one with Role and one without Role.

I had to change the view query to reflect the tasks without role and match the remaining hours to the previously assigned hours on the task. Now this became a major challenge. We had to export all the bookings from the system and delete the previous allocations on the task with role to the task without role. This would then match the remaining hours to allocate on the task.

The next things I did to make the tasks be treated as Non-Billable was to add the Column in the Schedule named Category, Wherein I added a Category named “Non-Billable”. This category was made Non-Chargeable.

This is the Transaction Category which can be added from SettingsàTransaction Categories.

I added a Calculated Field on the Project form then to calculate the Billable Hours which excluded this Non-billable Category task to see the correct Billable estimate of the project.

BI Team in your organization will now need to change the reports adjusting to the above criteria to reflect the correct data.

This blog reflects my personal findings and based solely on my experience of using PSA for last 3 years. For those who are looking for a platform that can track and manage the entire procedures of sales and project managements, I would highly recommend them to try Microsoft dynamics 365 for project service automation.

 

Written by

Kuldeep Gupta

Delivery Head

Leave a Reply

Your email address will not be published. Required fields are marked *

Want to streamline your business processes?

  • This field is for validation purposes and should be left unchanged.

Recent Articles

  • Integrate Dynamics 365 for Customer Engagement Apps with Microsoft Teams

    18 June’ 2019

    Before getting into details, firstly I would like to talk about Microsoft Teams. If you’re familiar with MS Teams, you...

    Read more
  • Applying Default / Mandatory Dimension in NAV / Business Central

    17 June’ 2019

    Introduction: In this blog, I aim to provide how to set Mandatory Dimensions on Items, Customers, Vendors, and G/L Accou...

    Read more
  • Automatically adding dimensions from Shortcut Dimension from Excel Import in Microsoft Dynamics NAV / Business Central

    17 June’ 2019

    Problem Statement: I have a requirement where the contents of the General Journals are to export to Excel and also can c...

    Read more
  • Using “startswith” Filter Query in MS Flow

    12 June’ 2019

    Introduction This blog explains how to use “startswith” filter query in MS Flow. Use Case Using MS Flows to retrieve...

    Read more
  • Print pro-forma invoice in Dynamics 365 Finance and Operations

    11 June’ 2019

    In this article I am going to demonstrate how to view/print  pro-forma invoice. A pro forma invoice is an invoice that ...

    Read more
  • We respect your privacy.
  • This field is for validation purposes and should be left unchanged.